FAA Audit finds lapses at Boeing, Spirit AeroSystems

Boeing 737 Max airpl­anes at the Rento­n Munic­ipal Airpo­rt in Rento­n, Wash., May 15, 2019. (Lindsey Wasson/The New York Times)
Boeing 737 Max airpl­anes at the Rento­n Munic­ipal Airpo­rt in Rento­n, Wash., May 15, 2019. (Lindsey Wasson/The New York Times)
minus
plus

WASHINGTON — The Federal Aviation Administration said on Monday that a six-week audit of Boeing and one of it key suppliers, Spirit AeroSystems, found “multiple instances” in which the companies failed to comply with quality-control requirements.


As part of the audit, which looked at production of the Boeing 737 Max, the FAA said that it had “identified noncompliance issues in Boeing’s manufacturing process control, parts handling and storage, and product control.” The regulator did not publicly release further details.


The FAA initiated the audit after a door panel came off a 737 Max 9 jet while at 16,000 feet in early January, raising new questions about quality-control practices at Boeing and Spirit, which makes the fuselage, or body, of the 737 Max.


Boeing declined to comment on the audit. A spokesperson for Spirit, Joe Buccino, said the company was reviewing the findings and was “in communication with Boeing and the FAA on appropriate corrective actions.”


The episode involving the door panel, known as a door plug, occurred on an Alaska Airlines flight shortly after it took off from Portland, Oregon, on Jan. 5. The FAA quickly grounded similar Max 9 jets, though the planes were allowed to return to service later that month after being inspected.


In a preliminary report last month, the National Transportation Safety Board said that four bolts used to secure the door plug had been removed from the jet at Boeing’s factory in Renton, Washington. The report suggested that the bolts might not have been reinstalled before the plane entered service.


The FAA’s audit was one of several steps that the regulator took in the aftermath of the door-plug episode to step up scrutiny of Boeing’s manufacturing processes. The agency also opened an investigation into whether the plane maker failed to ensure that its products were safe and conformed to their approved design, and it barred the company from increasing production of the 737 Max series until quality-control issues are addressed.


Last week, the FAA gave Boeing 90 days to develop a plan to improve its quality-control practices. In response, the company’s CEO, Dave Calhoun, said the plane maker had “a clear picture of what needs to be done,” adding that its leaders were “totally committed to meeting this challenge.”


A week earlier, Boeing announced a leadership shake-up in its commercial airplanes unit. And Friday, the company said it was in talks to acquire Spirit, which it spun out nearly two decades ago.


This article originally appeared in The New York Times.