PDO’s flagship Rabab Harweel Integrated Project completed

Petrofac Rabab Harweel2 rhip_1307-1-_1024x576
Petrofac Rabab Harweel2 rhip_1307-1-_1024x576
minus
plus

UK-based international oilfield engineering services contractor Petrofact has announce the successful completion of the Rabab Harweel Integrated Project (RHIP), one of the largest ventures of Petroleum Development Oman (PDO).


“Our Rabab Harweel Integrated Project (RHIP) team has received the completion certificate from Petroleum Development Oman (PDO) acknowledging successful delivery of the project,” said Petrofac in a statement.


Located in the Harweel cluster of fields, deep in the South Oman desert, the huge new development encompasses gathering systems, sour gas processing facilities, injection systems, and all the associated flowlines and pipelines.


Petrofac provided engineering, procurement, construction management and commissioning support services worth around $1.25 billion. It was the contractor’s first PDO project where a new commercial contract model (EPCm) was introduced. This meant it being delivered on a reimbursable basis, where incentives were linked to the achievement of specific milestones and a shared benefit on procurement savings.


“In-Country Value (ICV) was a critical consideration throughout the project. We exceeded all our targets for Omanisation. Also, more than a third of the project’s total procurement value was sourced in the Sultanate,” the company stated.


Khalid Abdul Kadar, Project Manager, has recently been leading the close out of the project, in parallel with his responsibilities on the Yibal Khuff project for PDO: “Achieving this milestone marks the successful completion of a six-year project journey. RHIP has also helped us to build on our existing long term partnership with PDO, which is now continued through Yibal Khuff and our other PDO Framework projects. This success is down to all the people involved and a One Team approach, particularly as we have had to overcome the recent COVID-19 related oil and gas industry challenges,” he said.