Orpic’s Mina Al Fahal Refinery shutdown till November 16

Orpic
Orpic
minus
plus

Orpic’s Mina Al Fahal Refinery currently undergoes a major planned turnaround and maintenance activity from October 3 until November 16 for 45 days. The shutdown will be used to execute a number of maintenance activities in order to


improve the operational performance of the refinery.


The maintenance operation is conducted every four years to improve performance. All requests were scheduled delivery of petroleum and petroleum products during the period specified, the company said.